Dispute Resolution HotlineFebruary 05, 2014 High Court v. District Court, Where will your Section 34 Arbitration Petition lie?
INTRODUCTION The Supreme Court (“SC”) in its recent judgment of Executive Engineer, Road Development Division No.III, Panvel & Anr. v Atlanta Limited1 has analysed the definition of “Court” to determine which court would hear challenges to an arbitral award (or arbitral agreement, or arbitral proceeding) where jurisdiction lies with more than one court and the parties initiate proceedings in multiple courts simultaneously. FACTUAL BACKGROUNDAtlanta Limited (“Respondent”) was awarded a contract for construction of the Mumbra bypass by the Public Works Department, Maharashtra (“Appellant”). The contract stipulated that in the event of disputes arising between the parties, the same were to be resolved through arbitration with the seat at Mumbai. Disputes arose between the parties in 2009, followed by an arbitral award being passed in 2012. This arbitral award was challenged under Section 34 of the Arbitration and Conciliation Act, 1996 (“Act”) before the District Judge, Thane by the Appellant and before the Bombay High Court (“Bombay HC”) by the Respondent on the same day, on August 7, 2012. The Respondent filed an application for transfer of proceedings from the District Judge, Thane to the Bombay HC as the subject-matter of challenge arose out of the same arbitral award. The application was allowed by the Bombay HC for consolidation leading to the present appeal. ISSUESThe SC dealt with two issues: Preliminary Issue: Whether a challenge to an arbitral award (wherein jurisdiction lies with more than one court), can be permitted to proceed simultaneously in two different Courts. Main Issue: Which of the two courts, viz. the Bombay HC or the District Judge, Thane would have jurisdiction to hear the matter if the answer to the preliminary issue is in the negative. ARGUMENTS BY THE APPELLANTIt was submitted that:
The Respondent contended that:
In respect of the preliminary issue, the SC, referring to Section 424 of the Act (although inapplicable in Part I disputes), stated that though the jurisdiction for raising a challenge to the same arbitration agreement, arbitral proceeding or arbitral award, could arise in more than one court simultaneously, the court where the first challenge application is filed will alone have the jurisdiction to adjudicate upon the dispute(s) which are filed later on. It was observed that in the present case Section 42 was not attracted since both the challenges had been filed on the same day. However, the SC held that it was clearly the legislative intention that all disputes arising out of same arbitral award would lie only before one court. Considering the submissions of the Appellant regarding the applicability of Section 15 of the CPC for the determination of the appropriate “Court” under the Act, the SC negatived the application of Section 15 for interpreting Section 2(1)(e) of the Act since, in the SC’s view, Section 15 of the CPC would defeat the inclusion of the High Court “in exercise of its ordinary original civil jurisdiction”, within the definition of the term “Court” as the “principal Civil Court of original jurisdiction in a district”, namely the District Judge concerned, being a court lower in grade than the High Court would always exclude the High Court from adjudicating upon the matter. The SC held that under the Act, it is the superior most Court exercising original civil jurisdiction, which would be termed as “Court” for the purpose of Section 2(1)(e) of the Act and negated arguments raised by the Appellant. The SC held that it makes no difference “if the principal civil court of original jurisdiction” is in the same district over which the High Court exercises original jurisdiction or some other district. Further, if an option is to be exercised between a High Court (under its “ordinary original civil jurisdiction”) on the one hand and a District Court (as “principal civil court of original jurisdiction”) on the other, the choice under the Act has to be exercised in favour of the High Court. ANALYSISIn this judgment the SC was posed with a very important issue of determining jurisdiction where parties file simultaneous challenges under the Act in more than one court, both of which enjoy jurisdiction to hear the matter. Though the conclusion may not have changed, the SC’s reasons in arriving at the conclusion appear to have overlooked some of the arguments made by the Respondent. The SC has failed to take into consideration the existing body of relevant case laws while resolving the query. The SC in its latest decision of Swastik Gases Private Limited v. Indian Oil Corporation Limited5 dealt with the issue of “exclusive jurisdiction” clauses in the context of arbitration and decided in favour of the court chosen by the parties. The SC did analyze the connecting factors shown by the parties however due to exclusive jurisdiction clause in agreement, decided otherwise. In the present case, the SC should have also considered the various courts in which the jurisdiction would have resided by establishing the connecting factors. Thereafter, it could have favoured the court with the strongest connecting factors for the purposes of hearing the challenges. In the context of arbitration the court with the strongest connection is the seat court, in this case the Bombay HC since the seat was Mumbai. Further, in para 18 of the decision, the SC holds that Section 15 of the CPC does not apply when interpreting 2(1) (e) of the Act since that would always oust the jurisdiction of the High Court and therefore the legislative intent in Section 2 (1)(e) differs from that behind Section 15. The High Court being the more superior court, the High Court would have jurisdiction. This interpretation can be distinguished on following counts – a) Although the judgment states that the question of pecuniary jurisdiction is not one before the Court, had the Court considered this question, it would’ve been amply clear that when the pecuniary ceiling of the District court is hit, even if the cause of action or subject matter is within the district, an applicant would be compelled to go to the High Court. b) Nothing in the language of Section 2 (1) (e) or the entire Act suggests that a hierarchically superior court will have jurisdiction. In fact reading Section 15, harmoniously with Section 2 (1) (e) it would have to be read in a manner which will result in different conclusion. c) In interpreting Section 2 (1) (e) the subject-matter of the arbitration has to be treated as if the same had been the subject-matter of a suit. Therefore, one could argue that Section 2 (1) (e) mandates that a petition be treated just as a suit for the purposes of interpreting the meaning of court. From such a reading as well, one could argue that a district court would be the first court of recourse and would aptly exercise jurisdiction. – Varuna Bhanrale, Payel Chatterjee, Shalaka Patil & Vyapak Desai You can direct your queries or comments to the authors 1 Civil Appeal No. 673 OF 2014 (Arising out of SLP (C) No.18980 of 2013) 2 Section 15 of the CPC: Court in which suits to be instituted: Every suit shall be instituted in the Court of the lowest grade competent to try it. 3 (2012) 9 SCC 559 4 Section 42 of the Act: Jurisdiction: Notwithstanding anything contained elsewhere in this Part or in any other law for the time being in force, where with respect to an arbitration agreement any application under this Part has been made in a Court, that Court alone shall have jurisdiction over the arbitral proceedings and all subsequent applications arising out of that agreement and the arbitral proceedings shall be made in that Court and in no other Court. 5 (2013) 9 SCC 32 DisclaimerThe contents of this hotline should not be construed as legal opinion. View detailed disclaimer. |
|