Dispute Resolution HotlineJune 13, 2012 Evidence of negotiation prior to settlement vitiates plea of duressBACKGROUND The Division Bench of the Hon’ble Delhi High Court in the case of Mecon Ltd. vs Pioneer Fabricators Pvt. Limited1 has held that settlement negotiations which lead to a no-claim letter would be sufficient evidence to show that the no-claim letter was executed without any undue influence. FACTS OF THE CASE Mecon Ltd. (“Appellant”) invited offers as per tender documents to construct five retail outlets for Indian Oil Corporation. The bid submitted by Pioneer Fabricators Pvt. Limited (“Respondent”) being the lowest was accepted and a contract styled as “Letter of Award” was entered into between the parties wherein the obligations of the parties were crystalized. The Letter of Award inter-alia provided that:
During execution of works on the site, the Appellant required the Respondent to execute 31 extra items of work and there were discussions between the parties with respect to the price to be paid in respect of the extra items of work as well as the actual work to be carried out at the sites (taking into account the work in respect of the extra work items). The Respondent submitted a final bill and as per which it raised a demand, pertaining to extra items of work, in sum of Rs. 1,05,05,374/- and Rs. 1,92,81,990.62/- for the works executed which were specifically quantified in detail in the Letter of Award. The Appellant verified this bill and there being certain discrepancies, reduced it to Rs. 2,88,74,334/- representing the total value of the work done. After adjusting running payments made to the Respondent pursuant to interim bills raised, finalized the amount payable to the Respondent was determined by the Appellant to be Rs. 57,41,541/-. The Respondent thereafter on February 14, 2003, sent a No-Claim Certificate in writing to Mecon as under:
Vide a subsequent letter dated March 5, 2003, the Respondent invoked the arbitration clause in the Letter of Award and for the first time contended that the No-Claim Certificate was issued under protest. However, in the said letter also, the Respondent did not take a stand that it was constrained to issue the No-Claim Certificate under duress. The Arbitrator, on the issue whether the Accord (No-Claim Certificate) was made under undue influence of the Appellant gave the following observation: “It also cannot be denied that the respondent (The Appellant herein) has been withholding a large sum due to the claimant (The Respondent herein) from payment and must have exercised undue influence on the claimant to agree to the respondents terms howsoever unfair.” The Arbitrator further recorded that the No-Claim Certificate issued by the Respondent was under protest and reserving its rights to other payments. ISSUE Whether the No-Claim Certificate issued after due deliberations could be voided by a party claiming duress and undue influence? JUDGMENT AND RATIONALE Whilst passing the judgment, the Division Bench of the Delhi High Court followed the ratio laid down in Chairman & MD NTPC Ltd. vs. M/s. Reshmi Constructions, Builder & Contractors2 wherein the Hon’ble Supreme Court had held that where there is evidence of the parties negotiating prior to a settlement taking place resulting in a full and final discharge voucher / receipt being executed, later-on the party executing the receipt cannot turn around and reprobate to claim that the settlement was not voluntary. The Hon’ble Court held that the fact that parties were in discussions on the issue of payment for the extra work items undertaken by the Appellant and the exact work to be executed where-after the Respondent submitted its final bill followed by the No-Claim Certificate would be “clear cut evidence” to show that there was an accord on all disputes between the parties which was arrived at after protracted correspondence and claims in respect of the disputes settled in the accord could not have been raised and the accord reopened. CONCLUSION For coming to a conclusion that the accord was indeed negotiated, the Hon’ble Court took note of the protracted correspondences held between the parties before which the No-Claim Certificate was issued by the Respondent to the Petitioner. The Court further highlighted that the observation made by the arbitral tribunal was cryptic and presumptive in as much as it had not discussed evidence on the accord i.e. the negotiations between the parties. It may be noted here that the reasoning behind the observation made by the Arbitrator that the No-Claim Certificate must have been procured by exercising undue influence is that the Appellant was withholding payment of large amount due to the Respondent. Therefore, the Principle enshrined in the present case is that if a party has negotiated an accord or settlement, it cannot later claim that it executed the said accord under undue influence or under duress and by implication the stronger bargaining position of other party would have no relevance.
DisclaimerThe contents of this hotline should not be construed as legal opinion. View detailed disclaimer. |
|